Things to be done

Following this post What needs to be finished I thought it would be a good idea to track this info just like I was tracking the timeline.  So I have reproduced the post here and I will cross out and comment on things as they go.

MISCELLANEOUS
Window aluminium infills. Following the re-bricking it is understood that the lintels in some locations have been installed higher than the top of the windows, resulting in a gap. Apparently this was necessary due to the large mortar gaps created by the previous brickie. Could you please provide details as to what will be done about these items and when these will be repaired. These have been done and you can hardly tell that they are there.
Privacy Locks. It is understood that the privacy locks will be installed this week. - Being done on 4/5/11 Need to check, toilet does not work properly needs review.
Hole above master bedroom. When viewing the house from the rear it is evident that there is a hole that is yet to be filled at the back end of the master bedroom gable. When will this be rectified. DONE
Sub floor insulation. Understood to be going in on Thursday. Almost finished on 5/5/11 some small gaps to be done. Found to be done on 1/6/11 Now just check ceiling insulation
Repair of corroded steelwork on lintels. It is noted that some of the steelwork used for the lintels has developed spot corrosion. How is this to be repaired and by when. These have been painted and they look passable.
Eaves around alfresco require repair. Due to the brick repair there is some work required on the eaves and timberwork around the alfresco. This will need to be replaced and repainted. One repaired, however there is still damage. All fixed now.
Front verandah eaves require repair. Due to the brick repair the ceiling of the verandah will require repair. Done 10/5/11
Warped steelwork above front verandah. The colourbond flashing above the front verandah contains a crease. When will this be repaired? *
Timber beading near master bedroom and other locations due to brick repair requires replacement. May be done, needs review. DONE
Bracket in Garage. There is a bracket in the front left corner of the garage as you enter which will need to be removed.  This has been cut off.
Sliding door beading. Currently there is no beading hiding the sliding door mechanism. This will need to be installed and painted appropriately. - Being installed on 4/5/11 Done Needs to painted. Painted nicely now.
Mortar Colour. I understand that the mortar will need to be recoloured. We agreed with your director that this could be done following hand over, however we require evidence that this has been ordered and paid for by The Builder. Started to be repaired on 12/5/11 still going there are some small patch repairs that need to be done.
Damp Proof Course. Due to the brick repairs there has been damage done to the Damp Proof Course membrane. A solution discussed with your Director was to apply an epoxy to seal this mortar. We require details of this solution and when it will be done. Similarly to the Mortar Colour this can be done following hand over, however we require evidence that it has been ordered and paid for by The Builder. Following further research there does not seem to be a product which allows for post construction installation of a DPC.  Therefore given that the DPC is mostly intact and that the DPC is so heigh above natural ground I am willing to accept this.  Sort of done.
Scratch on Drawer. There is a scratch on a drawer in the Bathroom Vanity.
Sealing WIP. There is a gap to the left of the bench in the walk in pantry. When will this be sealed?  This was sealed on 25/5/11
Sealing Brickwork. The expansion joints in the brickwork require sealing. When will this be done? DONE
Stain Glass windows. The stain glass windows in the bedroom need to be swapped with those in the lounge. DONE
Double doors to rumpus are damaged at base.  Painted Over.
Crack in corner of meals area in roof. Painted Over
Paint on picture rail near kitchen. Done
Termite Protection. When will this be done? * Spoke to SS on 1/6/11 and supposedly this is done, however will need to be done frequently.

PLUMBING
New toilets. It is understood that the new toilets will be installed on Tuesday or Wednesday this week. Just to clarify, these toilets are to be BTW toilets Reece code 9501855 Porcher Cygnet BTW Standard Close Coupled. Being done on 3/5/11 Need to check All Good
Plumbing of new toilets. It is assumed that the plumbing of these new toilets will be also performed on Tuesday or Wednesday. Being done on 3/5/11 Need to check All Good
Sealing of new toilets. It is assumed that the sealing of these new toilets will be also performed on Tuesday or Wednesday. Being done on 3/5/11 Need to check and they have cut the skirting boards in an ugly way. Fixed up skirting board, still need a seal around the toilet though.
Longer tap in bath. The current outlet for the bath in the bathroom is too short and is very close to the edge of the bath. Please provide details of the proposed new tap and when this will be installed. Done on 3/5/11
Repair of Downpipes. It is understood that the downpipes will be repaired on Tuesday or Wednesday. It should be noted that some of the stormwater drainage pipes at the base of the downpipes has been damaged during the brick repair and these will require repair. Being done on 3/5/11 Need to be painted They all look OK.

ELECTRICAL (provide timeframe for electrical work*)
Dimmers There do not appear to be any dimmers installed as per our selections.  Dimmers done, still need dimmer in dining room DONE
Power points in Vanities. The ensuite and bathroom vanities were to have power points inside them. This does not appear to have happened. Power point in bathroom, still need in ensuite. DONE
Microwave Power Point. There is no power point for the microwave in the walk in pantry. DONE
Stove GPO. Currently there are only two points for the ovens, there does not appear to be a powerpoint for the stove (we require 3 in total.) Still Unsure
Undercabinet light provision . It is not clear whether provision for undercabinet lighting has been provided. Still Unsure

Security System Power Point. There should be a power point for the security system in the walk in robe in the master bedroom. DONE but we still need the security system
Network hub. There does not appear to be a network connection in bed 4. There should be 7 network points. DONE 10/5/11
There needs to be a double GPO at the rear of the house. DONE
There needs to be a double GPO in the alfresco. DONE 10/5/11
The external electrical work still need to be completed. Can probably all be done on handover.
Need an aerial

PLASTERING
Repair of plaster for new toilets. Following removal of the new toilets it is understood that there may be some damage to the plaster. Please provide details as to when this repair will be done. Done on 5/5/11
Alfresco Ceiling. The cornices in the alfresco require replacement. When will this occur. DONE 10/5/11*
Cornice in Laundry. There is still a noticeable gap in the cornice in the laundry. This will require repair. DONE
Electrical Repair. Following the work performed by the electrician there is likely to be work required to repair plaster. DONE some minor blemishes. DONE

PAINTING
Repainting of lintels. Following the repair of the lintels from corrosion they will need to be repainted. When will this occur. DONE
Repainting of eaves around alfresco DONE
Painting of external paintwork that has been repaired. There will need to be multiple coats applied to all of the timber and cladding used to repair areas following the rebricking. When will this occur? DONE
Painting of render coat. The rough cast render on the master bedroom gable needs to be painted. DONE 17/5/11
Fix all painting throughout the house. The following items will need attention and need more coats:
repair of plaster from toilets / electrical / other
     Picture rail is not painted on the top It is done you just need to look down on it.
     Top and bottom of doors has been mostly done.
     Between the Walk in Wardrobe and the Master Ensuite the wall appears to only have one coat. DONE
     The Alfresco ceiling only appears to have one coat.
     Skirting boards have sander damage and some stain from the floorboards on them
     Other general areas will require attention.  DONE

FURTHER INFORMATION
Inclement weather. As we have heard no further information relating to inclement weather from The Builder regarding our estimate for inclement weather it is understood that The Builders have accepted our calculation of inclement weather of 14 days. Therefore the contractual finish date is 6/3/2011 based on your notice of commencement and the 10 days included for inclement weather within the contract. - May be sorted as of 4/5/11
Agreed Damages. Following from the above inclement weather we have calculated an agreed damages as per the contract as $2,442.85 as of today and a further $42.86 per calendar day from now on until all work meets the required specifications. May be sorted as of 4/5/11
Final Invoice. Until all items identified above, all items identified in our final inspection and any item identified by our independent inspection is fully rectified we will not be paying the final invoice. We also expect that this final invoice will include a deduction for the damages as detailed above. May be sorted as of 4/5/11 Received on 23/5/11. We will receive a cheque for the delay damages on hand over.
Documentation required. Further to contractually required documentation could you also provide the truss design documentation that you would have received from the truss suppliers.  We need something from the electrician to prove that the downlight covers are OK.
Independent Inspector. Due to the poor workmanship that has been found in some areas we have opted to engage an independent inspector. Could you please let us know when the best time to have them review the house is. Inspector booked fro Friday 20/5/11*

If you require any clarification relating to the above please do not hesitate to contact me.

After I sent the above info I realized I'd still managed to leave some items out. So I sent a second email.

Further to the previous email the following items also need to be attended to:
Garage Doors - Going in on 9/5/11 - Need review
Ducted Heating
Ducted Vacuuming Machine installed, need treatments at vacuum points. DONE
Hot water booster for solar hot water
Staining of Alfresco Decking started 16/5/11 DONE
Covers for ceiling entry manholes. Seem to have been made.
Levelling of site, particularly around alfresco pillars and rear of house where water is pooling under North West corner. Seems to have been done, however the South side looks a mess.
Appliance Fit Off including fitting of three lights to front of house. Please provide us with an expected time that you require delivery.
The paintwork on the front door appears to include lots of little white dots. Should have been done 17/5/11 needs review. DONE
Installation of temporary stairs - Being done 4/5/11 front only however this is sufficient
Softclosing hinges for kitchen and bathroom cupboards.  Need to order number from Cabinet people and I will install. Have been supplied just need Room4acubby soft closing installation service to perform their duty.