Monday, October 25, 2010

Doors arrived

Popped by this evening to see what has been happening.  Our brickie is back and progressing.  He's up to the soldier course (vertical highlight bricks) under the lounge room window.

Inside the doors have been delivered.  There were 11 tall doors and 11 short doors.  The architraves were delivered, along with a manhole lining.

1 comment:

  1. Nice to see some more progress, I can't believe you have only one brickie on site, is it any wonder things are taking so long!! You must be very frustrated. We were told it would be about 7 months to build the Jamieson.

    ReplyDelete